Follow the instructions given in the Overview and Video Tutorials to complete Part 5 (Do only the Fourth Quarter, January 1, 2011) and Part 6 of the Conveyor Belt Project in Appendix 2 of the text book. Submit Part 5 as a Word document by the end of Module Eight. Part 6 will be submited in Module Nine, but it is recommended that you begin work on Part 6 in this module.

Initial Steps

  1. Open the Conveyor Belt Project file for the homework from the last module (resource scheduling).

  2. Save the file under a new name. So you can go back to the previous file if there is a problem afterwards.

  3. Set baseline for the project.

  4. Open a Word document for this week’s homework.

Part 5 (Do only the Fourth Quarter, January 1, 2011)

  1. Set status and current date for the project to January 1, 2011.

  2. Enter status information for the project in the Tracking table.

  3. Produce and copy/ paste the Earned Value Report, Earned Value Cost Indicators Report, Earned Value Schedule Indicators Report and the Tracking Gantt Chart into the Word document.

  4. Answer all the questions given in Part 5 for the fourth quarter only. Note: EACf is same as EAC and VACf is same as VAC.

Part 6 (Status Date January 1, 2011)

  1. There is no need to change the status and current date from what was set earlier, i.e., January 1, 2011.

  2. Enter the new status information for the project in the Tracking table.

  3. Produce and copy/ paste the Earned Value Report, Earned Value Cost Indicators Report, Earned Value Schedule Indicators Report and the Tracking Gantt Chart into the Word document.

  4. Answer all the questions given in Part 6.